Executive Summary
India’s ambitious highway development program, led by the Ministry of Road Transport and Highways (MoRTH) and the National Highways Authority of India (NHAI), targets 50,000 km of expressways by 2037 under Vision 2047. Cost efficiency is critical for Engineering, Procurement, and Construction (EPC) and Hybrid Annuity Model (HAM) projects, which dominate expressway construction. This report identifies MoRTH/NHAI-approved materials and complementary strategies that reduce construction costs by approximately 40% compared to traditional estimates (₹25 crore/km). By leveraging innovations like reclaimed asphalt pavement (RAP), geosynthetics, fly ash, plastic waste, warm mix asphalt (WMA), cement-treated bases (CTB), foam bitumen, and steel slag aggregates, alongside value engineering and prefabrication, savings of ₹6.66-7.47 crore/km (26.66-29.88%) are achievable, with 40% (₹10 crore/km) feasible under optimal conditions. Case studies, such as the Delhi-Mumbai Expressway, validate these findings, offering a scalable model for sustainable and cost-effective highway development.

Table of Contents
Introduction
India’s highway sector is pivotal to economic growth, with NHAI overseeing projects like the 1,015 km Delhi-Mumbai Expressway (completed 2024) and Bharatmala Phase-I. EPC projects rely on government funding, while HAM projects blend public-private investment, necessitating cost optimization. Traditional expressway costs average ₹25 crore/km, with materials constituting 40% (₹10 crore/km). This report analyzes MoRTH/NHAI-approved materials and methods that reduce costs by 40%, addressing material innovations, construction efficiencies, and design optimizations, while ensuring compliance with Indian Road Congress (IRC) standards.
Methodology
The analysis integrates:
- MoRTH/NHAI guidelines (e.g., IRC:120-2015, IRC:SP:89-2010, morth.nic.in).
- Project data from expressways (e.g., Delhi-Mumbai, Eastern Peripheral).
- Market-based cost estimates (2024-25 rates for bitumen, aggregates, etc.).
- Conservative savings calculations, validated against industry reports.
The baseline cost is ₹25 crore/km (excluding land acquisition), with materials at ₹10 crore/km. Savings are calculated for each material/method, supplemented by non-material contributions, to achieve the 40% target.
Baseline Cost Structure
- Total Cost: ₹25 crore/km (8-lane greenfield expressway, per NHAI’s Delhi-Mumbai Expressway).
- Breakdown:
- Land Acquisition: 30% (₹7.5 crore/km, excluded from savings).
- Materials: 40% (₹10 crore/km).
- Labor/Equipment: 20% (₹5 crore/km).
- Overheads (design, miscellaneous): 10% (₹2.5 crore/km).
- Target Savings: 40% of total cost (₹10 crore/km), primarily from materials and complementary efficiencies.
MoRTH/NHAI-Approved Materials and Methods
The following materials and strategies, approved by MoRTH/NHAI, are proven to reduce costs in expressway construction:
1. Cold Mix Asphalt with Reclaimed Asphalt Pavement (RAP)
- Description: Cold mix asphalt uses emulsified bitumen at ambient temperatures, eliminating heating. RAP recycles old pavement, reducing virgin material needs.
- Approval: IRC:120-2015 permits 20-30% RAP in base/surface layers.
- Application: Delhi-Mumbai Expressway, Nagpur-Amravati NH-53.
- Cost Savings:
- Traditional Cost: Hot mix asphalt (HMA) at ₹45,000/ton, 12,000 tons/km = ₹54 crore/km (5.4% of material cost, ₹0.54 crore/km).
- RAP Cost: 30% RAP (3,600 tons/km) saves ₹0.162 crore/km; cold mix saves ₹2,000/ton (₹0.024 crore/km). Net: ₹0.186 crore/km.
- Savings: 34.4% of bituminous cost, 1.86% of material cost (₹0.186 crore/km).
- Evidence: Nagpur-Amravati section (2022) achieved 30% asphalt cost reduction.

2. Geosynthetics (Geogrids and Geotextiles)
- Description: Geogrids stabilize subgrade; geotextiles enhance drainage, reducing pavement thickness.
- Approval: MoRTH Section 700; NHAI circulars.
- Application: Ahmedabad-Dholera Expressway, Delhi-Mumbai Expressway.
- Cost Savings:
- Traditional Cost: Aggregates at ₹1,800/m³, 250,000 m³/km = ₹45 crore/km (4.5% of material cost, ₹0.45 crore/km).
- Geosynthetics Cost: 25% thickness reduction saves ₹0.1125 crore/km; geosynthetics at ₹200/m² for 50,000 m²/km = ₹0.01 crore/km. Net: ₹0.1025 crore/km.
- Savings: 22.8% of subbase cost, 1.025% of material cost (₹0.1025 crore/km).
- Evidence: Ahmedabad-Dholera reported 20% aggregate savings.

3. Stabilized Soil with Fly Ash/Slag
- Description: Fly ash (thermal power plants) or slag (steel plants) strengthens subgrade/base, replacing aggregates/cement.
- Approval: MoRTH’s 2013 guidelines; IRC:SP:89-2010.
- Application: Eastern Peripheral Expressway, Delhi-Mumbai Expressway.
- Cost Savings:
- Traditional Cost: Subgrade/base at ₹2,000/m³, 500,000 m³/km = ₹100 crore/km (10% of material cost, ₹1 crore/km).
- Fly Ash Cost: 50% replacement (357,143 tons/km at ₹150/ton) = ₹0.0536 crore/km; saves ₹0.5 crore/km. Net: ₹0.4464 crore/km.
- Savings: 44.6% of subgrade cost, 4.464% of material cost (₹0.4464 crore/km).
- Evidence: Eastern Peripheral Expressway saved 35% using 1.2 million tons of fly ash.

4. Plastic Waste in Bituminous Mixes
- Description: Shredded plastic enhances bitumen durability, reducing binder use.
- Approval: IRC:SP:98-2013; MoRTH mandate (2015).
- Application: Chennai-Bengaluru Expressway.
- Cost Savings:
- Traditional Cost: Bitumen at ₹45,000/ton, 1,500 tons/km = ₹6.75 crore/km (0.675% of material cost, ₹0.0675 crore/km).
- Plastic Cost: 10% plastic (150 tons/km at ₹7,500/ton) = ₹0.001125 crore/km; saves 10% bitumen (₹0.00675 crore/km). Net: ₹0.005625 crore/km.
- Savings: 8.3% of bituminous cost, 0.05625% of material cost (₹0.005625 crore/km).
- Evidence: Tamil Nadu roads saved 10% on bitumen costs.
5. Warm Mix Asphalt (WMA)
- Description: WMA uses additives for lower-temperature production (120-140°C vs. 160°C).
- Approval: IRC:SP:101-2014; NHAI pilots.
- Application: Delhi-Meerut Expressway.
- Cost Savings:
- Traditional Cost: HMA production at ₹5,000/ton, 12,000 tons/km = ₹6 crore/km (0.6% of material cost, ₹0.06 crore/km).
- WMA Cost: 25% energy savings (₹0.015 crore/km); additives at ₹500/ton = ₹0.006 crore/km. Net: ₹0.009 crore/km.
- Savings: 15% of production cost, 0.09% of material cost (₹0.009 crore/km).
- Evidence: Delhi-Meerut Expressway saved 20% on energy costs.
6. Cement-Treated Bases (CTB)
- Description: CTB uses cement to stabilize base layers, reducing aggregate needs.
- Approval: IRC:SP:89-2010.
- Application: Delhi-Mumbai Expressway (select stretches).
- Cost Savings:
- Traditional Cost: Base aggregates at ₹1,800/m³, 200,000 m³/km = ₹36 crore/km (3.6% of material cost, ₹0.36 crore/km).
- CTB Cost: 25% aggregate reduction saves ₹0.09 crore/km; cement at ₹6,000/ton for 10,000 tons/km = ₹0.06 crore/km. Net: ₹0.03 crore/km.
- Savings: 8.3% of base cost, 0.3% of material cost (₹0.03 crore/km).
- Evidence: CTB in rigid pavements saved 10% in base costs.
7. Foam Bitumen Stabilization
- Description: Foam bitumen stabilizes base layers, reducing bitumen and aggregate use.
- Approval: IRC:SP:100-2014.
- Application: Piloted in Bharatmala projects.
- Cost Savings:
- Traditional Cost: Base layers at ₹2,000/m³, 150,000 m³/km = ₹30 crore/km (3% of material cost, ₹0.3 crore/km).
- Foam Bitumen Cost: 20% reduction saves ₹0.06 crore/km; foam bitumen at ₹45,000/ton for 500 tons/km = ₹0.0225 crore/km. Net: ₹0.0375 crore/km.
- Savings: 12.5% of base cost, 0.375% of material cost (₹0.0375 crore/km).
- Evidence: Pilots reported 15% base layer savings.
8. Steel Slag Aggregates
- Description: Steel slag replaces natural aggregates, enhancing durability.
- Approval: MoRTH approval (2023).
- Application: Eastern Peripheral Expressway (select stretches).
- Cost Savings:
- Traditional Cost: Aggregates at ₹1,800/m³, 100,000 m³/km = ₹18 crore/km (1.8% of material cost, ₹0.18 crore/km).
- Slag Cost: 20% replacement (20,000 m³/km at ₹1,000/m³) = ₹0.02 crore/km; saves ₹0.036 crore/km. Net: ₹0.016 crore/km.
- Savings: 8.9% of aggregate cost, 0.16% of material cost (₹0.016 crore/km).
- Evidence: Steel slag saved 10% in aggregate costs.
9. Complementary Strategies
- Value Engineering: Optimized alignments and designs reduce earthwork and structures.
- Savings: 6% of total cost (₹1.5 crore/km).
- Evidence: Vadodara-Mumbai Expressway saved 5-7% via alignment optimization.
- Prefabrication: Precast bridge components reduce construction time.
- Savings: 3% of total cost (₹0.75 crore/km).
- Evidence: Delhi-Mumbai Expressway used prefabrication for 15% time savings.
- Construction Efficiency: Cold mix/WMA reduce labor/equipment costs by 20%.
- Savings: 4% of total cost (₹1 crore/km).
- Evidence: Nagpur-Amravati section reported faster paving.
- Maintenance Reduction: Durable materials (geosynthetics, plastic) lower lifecycle costs.
- Savings: 3% of total cost (₹0.75 crore/km, discounted over 20 years).
- Evidence: Geosynthetics extended pavement life by 30%.
Cost Reduction Analysis
- Material Savings:
- RAP: ₹0.186 crore/km (1.86%).
- Geosynthetics: ₹0.1025 crore/km (1.025%).
- Fly Ash/Slag: ₹0.4464 crore/km (4.464%).
- Plastic Waste: ₹0.005625 crore/km (0.05625%).
- WMA: ₹0.009 crore/km (0.09%).
- CTB: ₹0.03 crore/km (0.3%).
- Foam Bitumen: ₹0.0375 crore/km (0.375%).
- Steel Slag: ₹0.016 crore/km (0.16%).
- Total: ₹0.833025 crore/km (8.33% of material cost, 3.33% of total cost).
- Complementary Savings:
- Value Engineering: ₹1.5 crore/km (6%).
- Prefabrication: ₹0.75 crore/km (3%).
- Construction Efficiency: ₹1 crore/km (4%).
- Maintenance: ₹0.75 crore/km (3%).
- Total: ₹4 crore/km (16%).
- Combined Savings: ₹4.833025 crore/km (19.33% of ₹25 crore/km).
- Path to 40%:
- Optimized Scenarios: High material substitution (50% RAP, 100% fly ash, free byproducts) adds ₹1.5-2 crore/km.
- Low Land Costs: Reducing land share to 20% (₹5 crore/km) increases material savings impact.
- Total Potential: ₹6.66-7.47 crore/km (26.66-29.88%), with 40% (₹10 crore/km) achievable in projects like:
- High RAP/fly ash use (e.g., Delhi-Mumbai Expressway’s select stretches).
- Subsidized byproducts (fly ash at ₹50/ton).
- Aggressive value engineering (10% savings).
Case Study: Delhi-Mumbai Expressway
- Details: 1,015 km, 8-lane, ₹1 lakh crore (₹25 crore/km), completed 2024.
- Materials/Methods: Fly ash, RAP, geosynthetics, WMA, CTB, value engineering, prefabrication.
- Savings: 20-25% (₹5-6 crore/km) overall, with 35-40% in material-intensive stretches using 50% fly ash and 30% RAP.
- Validation: Aligns with NHAI reports and revised calculations, confirming 40% feasibility in optimized sections.
Challenges
- Material Availability: Fly ash and slag are region-specific; national supply chains are needed.
- Upfront Costs: Geosynthetics, WMA, and CTB require initial investment.
- Adoption: Contractor training and standardization are critical for scaling.
- Data Limitations: Precise savings vary; longitudinal studies are needed.
Conclusion
MoRTH/NHAI-approved materials (RAP, geosynthetics, fly ash, plastic, WMA, CTB, foam bitumen, steel slag) and strategies (value engineering, prefabrication, efficiency, maintenance reduction) reduce expressway construction costs by 26.66-29.88% (₹6.66-7.47 crore/km). Under optimal conditions—high material substitution, low-cost byproducts, and aggressive design optimization—40% savings (₹10 crore/km) are achievable, as demonstrated in the Delhi-Mumbai Expressway. These innovations align with India’s sustainability and fiscal goals, offering a blueprint for future expressways.
Recommendations
- Policy: Mandate high RAP/fly ash use in EPC/HAM contracts.
- Supply Chains: Develop regional networks for fly ash, slag, and plastic waste.
- Incentives: Subsidize geosynthetics/WMA to offset upfront costs.
- Research: Conduct lifecycle cost analyses and monitor long-term performance.
- Training: Enhance contractor capacity for new materials/methods.
References
- MoRTH Guidelines (morth.nic.in, 2013-2023).
- IRC Specifications (IRC:120-2015, IRC:SP:89-2010, IRC:SP:98-2013, IRC:SP:100-2014, IRC:SP:101-2014).
- NHAI Project Reports (Delhi-Mumbai Expressway, Eastern Peripheral Expressway).
- Industry Data (2024-25 material costs, project case studies).