Purpose: To provide a standardized procedure for Assistant Engineers (AE) or Construction Site Controllers (CSC) to conduct periodic Site Quality Audits and issue Non-Conformance Reports (NCRs) for deviations in materials or workmanship, ensuring compliance with MoRTH, IRC, IS codes, and ISO 9001:2015.
Scope: Applicable to all road construction projects in India, including earthwork, sub-base, base course, bituminous layers, concrete pavements, and associated works.
Document Version: 2.0
Publication Date: June 09, 2025
Approval Authority: [Insert Name/Designation, e.g., Project Director]
Applicable Standards:
- MoRTH Specifications for Road and Bridge Works (5th Revision, 2013)
- IRC: SP: 57-2018 – Guidelines on Quality Systems for Roads
- IRC: SP: 47-2014 – Guidelines on Quality Systems for Road Bridges
- IRC: SP: 55-2014 – Guidelines on Traffic Management in Work Zones
- IRC: SP: 98-2013 – Guidelines for Use of Waste Materials in Road Construction
- IS: 383-2016, IS: 73-2013, IS: 269-2015, IS: 2720 (Parts 5, 8, 28), IS: 456-2000, IS: 1786-2008, IS: 1199-1959, IS: 516-1959, IS: 6241-1971
- ISO 9001:2015 – Quality Management Systems
1. Preparation for Site Quality Audit
Objective
To plan and allocate resources for effective quality audits at specified intervals or construction stages.
Steps
- Review Project Documents:
- Examine the Quality Assurance Plan (QAP), Inspection Test Plan (ITP), and contract specifications (MoRTH Clause 901.1).
- Identify critical stages (e.g., embankment, WMM, bituminous surfacing) for audits, per IRC: SP: 57-2018.
- Conduct Risk Assessment:
- Identify potential quality risks (e.g., material shortages, equipment failures) using a risk matrix (ISO 9001:2015 Clause 6.1).
- Prioritize high-risk areas (e.g., concrete pavements, MoRTH Section 600) for detailed audits.
- Schedule Audits:
- Plan audits monthly or at milestones (e.g., sub-base completion), per MoRTH Clause 901.3.
- Coordinate with contractor, client, and third-party auditors (if applicable) for site access.
- Prepare Audit Tools:
- Use the Site Quality Audit Checklist .
- Arrange testing equipment (e.g., sand replacement kit, slump cone, bitumen extractor).
- Set up digital tools (e.g., Procore, NIC’s e-Office) for record-keeping, per MoRTH Clause 901.4.
- Form Audit Team:
- Assign AE/CSC as lead auditor, supported by quality engineers, lab technicians, and third-party auditors (if required, MoRTH Clause 901.3).
- Brief team on standards (MoRTH Sections 300-900, IS: 456, IS: 2720) and risk priorities.
Responsibilities
- AE/CSC: Plan audit, conduct risk assessment, and lead team.
- Contractor: Provide site access, materials, and quality records.
- Client: Approve audit schedule and third-party involvement.
- Quality Engineer: Assist in testing and documentation.
2. Conducting the Site Quality Audit
Objective
To verify compliance of materials, workmanship, and processes with specified standards through inspections and testing.
Steps
- Site Inspection:
- Inspect ongoing/completed work (e.g., embankment, WMM, bituminous layers) for visual defects, per MoRTH Clause 902.
- Measure layer thickness, surface regularity, and camber using tools like measuring tapes and 3m straightedges (MoRTH Clauses 305, 406, 507).
- Material Verification:
- Check test certificates for aggregates (IS: 383-2016), bitumen (IS: 73-2013), cement (IS: 269-2015), and steel (IS: 1786-2008).
- Conduct random sampling for lab/field tests if certificates are missing or doubtful (MoRTH Clause 901.2).
- Verify use of sustainable materials (e.g., recycled aggregates, IRC: SP: 98-2013).
- Field Testing:
- Perform field density tests (min. 1 test per 500 sq.m for embankment/WMM, IS: 2720 Part 28).
- Conduct bitumen content tests (min. 1 test per 100 tonnes, IS: 6241-1971).
- Verify concrete slump (50-100 mm, IS: 1199-1959) and compressive strength (IS: 516-1959) for PQC.
- Workmanship Assessment:
- Confirm compaction (min. 95% MDD for embankment, MoRTH Clause 305.3).
- Verify bituminous layer application (mixing temp 150-165°C, MoRTH Clause 507).
- Check surface regularity (max. 4 mm under 3m straightedge, MoRTH Clause 902.3).
- Safety and Environmental Compliance:
- Ensure PPE usage (helmets, vests, IS: 2925-1984) and dust control (water sprinkling, MoRTH Clause 111.1).
- Verify erosion control (silt fences, MoRTH Clause 306) and waste management (MoRTH Clause 111.4).
- Confirm traffic management (signage, barriers, IRC: SP: 55-2014).
- Documentation Review:
- Verify quality control records, ITP adherence, and daily reports (MoRTH Clause 901.4).
- Ensure digital records are backed up (e.g., cloud-based systems).
Responsibilities
- AE/CSC: Lead inspection, verify compliance, and record findings.
- Quality Engineer: Conduct tests and assist in documentation.
- Contractor: Provide materials, equipment, and records.
- Third-Party Lab: Conduct independent tests if required.
3. Identification and Documentation of Non-Conformances
Objective
To identify and document deviations from standards for corrective action.
Steps
- Identify Deviations:
- Compare findings with standards (e.g., MoRTH Clauses 305, 406, 507; IS: 456).
- Flag issues like low compaction, incorrect bitumen content, or non-compliant slump.
- Classify Severity:
- Minor: Minimal impact (e.g., slight surface irregularity, MoRTH Clause 902).
- Major: Structural impact (e.g., low concrete strength, IS: 516).
- Critical: Immediate safety/structural risk (e.g., embankment failure).
- Document Non-Conformance:
- Use the NCR format (artifact ID: d1867d3d-27b4-4f80-8321-578fd627c847).
- Record details: location, description (e.g., “WMM thickness 60 mm vs. 75 mm”), standard violated (MoRTH Clause 406), and evidence (test reports, photos).
- Issue NCR:
- For standard NCRs, issue within 24 hours to contractor and project manager.
- For critical NCRs, issue immediately, halt work if necessary (MoRTH Clause 901.5), and notify client.
- Log NCR in quality management system (e.g., Procore, Excel).
Responsibilities
- AE/CSC: Identify deviations, classify severity, and issue NCR.
- Contractor: Acknowledge NCR and provide initial response.
- Client: Review critical NCRs and approve work stoppage if needed.
4. Root Cause Analysis and Corrective Action
Objective
To determine causes of non-conformances and implement corrective actions.
Steps
- Conduct Root Cause Analysis:
- Collaborate with contractor to analyze issues (e.g., equipment failure, operator error) using 5-Why or fishbone analysis (ISO 9001:2015 Clause 8.7).
- Review records (e.g., batching plant logs, test results).
- Propose Corrective Actions:
- Specify actions (e.g., “Replace non-compliant WMM, retest density per IS: 2720”).
- Set completion date and assign responsibilities (e.g., contractor’s site engineer).
- Document in NCR:
- Update NCR with root cause, corrective actions, and verification method (e.g., retest per IS: 6241).
- Monitor Implementation:
- Verify corrective actions within timeline (MoRTH Clause 901.5).
- Conduct follow-up tests/inspections to confirm compliance.
Responsibilities
- AE/CSC: Oversee analysis, approve actions, and monitor implementation.
- Contractor: Perform corrective actions and provide evidence.
- Quality Engineer: Assist in verification tests.
5. Preventive Measures and NCR Closure
Objective
To prevent recurrence and formally close NCRs.
Steps
- Propose Preventive Measures:
- Identify solutions (e.g., “Train operators on bitumen sprayer calibration,” MoRTH Clause 112).
- Update QAP/ITP with additional checks (IRC: SP: 57).
- Implement Preventive Measures:
- Schedule training or maintenance (e.g., “Training on [Date]”).
- Document implementation (e.g., “Pre-mix checklist introduced”).
- Verify Compliance:
- Conduct retests (e.g., slump per IS: 1199, density per IS: 2720).
- Confirm compliance (e.g., “Slump 80 mm, per IS: 456”).
- Close NCR:
- Update NCR status to “Closed” upon verification (MoRTH Clause 901.5).
- Attach documents (test reports, photos) and obtain signatures.
- Archive NCR digitally (MoRTH Clause 901.4).
Responsibilities
- AE/CSC: Approve measures, verify compliance, and close NCR.
- Contractor: Implement measures and provide evidence.
- Client: Review closed NCRs for major/critical issues.
6. Reporting and Continuous Improvement
Objective
To document outcomes, share findings, and enhance quality processes.
Steps
- Compile Audit Report:
- Summarize findings, NCRs, and recommendations in the audit checklist.
- Include next audit schedule and approval signatures.
- Share with Stakeholders:
- Distribute reports to contractor, client, and quality control committee (via email, e-Office, or Procore).
- Upload to project portal (MoRTH Clause 901.4).
- Conduct Review Meetings:
- Hold monthly quality meetings to discuss NCR trends and preventive measures (IRC: SP: 57).
- Update QAP based on feedback (MoRTH Clause 901.1).
- Change Management:
- Review methodology annually or upon regulatory changes (e.g., MoRTH updates).
- Document revisions with version control and client approval.
- Train Personnel:
- Conduct training on standards and NCR processes (MoRTH Clause 112).
- Use NCR case studies to improve awareness.
Responsibilities
- AE/CSC: Prepare reports, lead meetings, and manage revisions.
- Contractor: Participate in meetings and implement QAP updates.
- Client: Approve reports and methodology revisions.
- Quality Control Committee: Review KPIs and recommend improvements.
7. Tools and Resources
- Testing Equipment: Sand replacement kit, slump cone, core cutter, bitumen extractor, compression testing machine.
- Documentation Tools: Audit Checklist, NCR format, digital platforms (Procore, e-Office, Excel).
- Standards: MoRTH Specifications, IRC: SP: 57, IS codes, ISO 9001:2015.
8. Key Performance Indicators (KPIs)
- Audit Completion Rate: 100% of planned audits completed.
- NCR Closure Rate: 95% of NCRs closed within timeline.
- Non-Conformance Rate: Reduce major/critical NCRs by 10% quarterly.
- Testing Compliance: 100% adherence to testing frequencies (MoRTH Clause 903).
- Sustainability Metrics: 10% use of recycled materials where applicable (IRC: SP: 98).
9. Publication and Distribution
- Format: Publish as a PDF document with version control and approval signatures.
- Distribution: Share via project portals (e.g., morth.nic.in, e-Office), contractor’s quality system, and printed copies for site use.
- Accessibility: Ensure availability to all stakeholders, including client, contractor, and third-party auditors.
- Archiving: Maintain digital copies in project records for at least 5 years, per MoRTH Clause 901.4.
References
- MoRTH Specifications for Road and Bridge Works (5th Revision, 2013)
- IRC: SP: 57-2018 – Guidelines on Quality Systems for Roads
- IRC: SP: 47-2014 – Guidelines on Quality Systems for Road Bridges
- IRC: SP: 55-2014 – Guidelines on Traffic Management in Work Zones
- IRC: SP: 98-2013 – Guidelines for Use of Waste Materials in Road Construction
- IS: 383-2016 – Coarse and Fine Aggregates for Concrete
- IS: 73-2013 – Paving Bitumen
- IS: 269-2015 – Ordinary Portland Cement
- IS: 2720 – Methods of Test for Soils (Parts 5, 8, 28)
- IS: 456-2000 – Plain and Reinforced Concrete
- IS: 1786-2008 – High Strength Deformed Steel Bars
- IS: 1199-1959 – Methods for Sampling and Analysis of Concrete
- IS: 516-1959 – Methods for Tests for Strength of Concrete
- IS: 6241-1971 – Method of Test for Determination of Bitumen Content
- ISO 9001:2015 – Quality Management Systems
Approval
Prepared By: [Insert Name, AE/CSC]
Reviewed By: [Insert Name, Quality Control Committee Lead]
Approved By: [Insert Name, Project Director/Client]